GROUP ACTIVITIES – PLANNING FOR AUDITING #
Scenario #
Your client has applied for Group Certification under MSPO.
The Group consists of 3 Sites, each containing 4 Estates:
- Site 1: Estate 1, Estate 2, Estate 3, Estate 4
- Site 2: Estate 1, Mill 2, Estate 3, Estate 4
- Site 3: Estate 1, Estate 2, Estate 3, Estate 4
Only use the information provided above.
Anything not provided is NOT APPLICABLE.
GROUP FORMATION #
All participants will be divided into 3 groups, assigned as:
- Group 1 → Site 1
- Group 2 → Site 2
- Group 3 → Site 3
Each group will plan the MSPO audit for their assigned Site only, based on the scenario.
TEAM LEADER APPOINTMENT & ROLE ASSIGNMENT #
Within each group:
1. Appoint ONE Team Leader #
The Team Leader must:
- Coordinate discussion
- Assign specific roles to each member
- Ensure the output follows the 5 required components
- Prepare the group presentation
2. Roles #
Team Leader may assign roles such as:
- Audit Programme & Cycle Coordinator
- Scope & Certification Route Coordinator
- Audit Team Composition & Competency Coordinator
- Risk Assessment & Sampling Coordinator
- Audit Duration & Man-Day Coordinator
- Document Compiler / Presenter (optional)
Roles must be based ONLY on the activity components.
TASKS FOR EACH GROUP #
Use only scenario data and applicable MSPO Scheme clauses.
1. Audit Programme & Cycle #
Group must determine:
- Is the audit: Stage 1, Stage 2, Surveillance or Recertification?
- Required stages based on MSPO audit cycle.
2. Scope & Certification Route (Group Certification) #
Group must identify:
- Certification Scope = Their assigned Site (4 Estates)
- Eligibility for Group Certification (Group Manager + multiple sites)
No additional operational details needed.
3. Audit Team Composition & Competency #
Group prepares:
- Lead Auditor
- Auditor(s)
- Optional Technical Expert – Only role structure, no personal data.
- Address qualifications criteria of each persons
4. Risk Assessment & Sampling Plan #
Based strictly on:
- 1 Site
- 4 Estates
Group must determine sampling for that Site based on justified risk rating
Note: Participants may use any recognised application to determine the conclusion of the exercise, such as
5. Audit Duration & Man-Days #
Based on:
- One assigned Site
- Four Estates
Group calculates man-days using only this information (no additional data such as hectares or workers).
EXPECTED OUTPUT FOR PRESENTATION #
Each group must present 5 items:
- Audit Programme & Cycle
- Scope & Certification Route
- Audit Team Structure
- Risk Assessment justification
- Sampling Plan
- Audit Duration & Man-Days
Refer to MSPO Certification Scheme Document as a guidance
Presentation Time: 5–7 minutes per group